After many years of needing new public safety buildings, the end is in sight.

YOUR FIRE DEPARTMENT

Due to the cold weather, the concrete pads have not been completed.  As of today, January 19, 2015 progress is being made with the concrete.  After the concrete has been pored for the Fire Department building it will require 30 days to cure.  Because of the weight of the fire trucks  this process takes longer than normal.   The updated estimate of the move  is mid March pending no weather delays.

 

DSCN0243      DSCN0244

 

FD1

 

 

Displaying Fire04.jpg

 

 

 YOUR POLICE DEPARTMENT

 

DSCN0245            

 

 