PROJECT: Clay Street Sewer Phase II (Sycamore Street Phase).

  • UPDATE (June 14, 2019):  Ten (10) residents affected. Sycamore Street has road cut ready for excavation. Area behind 300 Block of South Lynn cleared with tree removal and brush clearing. Some fence removed. Residents notified of construction schedule.  

PROJECT DESCRIPTION: Installation of 8″ sewer main and connection of private sewer services in the 300 Block of South Lynn and 400 Block of East Sycamore.


PROJECT: Clay Street Sewer Phase II.

  • UPDATE (June 10, 2019): Sewer line and services installation completed. Ground clean-up finished. Street cuts, driveways and curb/gutter are not completed.
  • UPDATE (April, 15 2019): 880′ of line installed. Four (4) manholes placed. Services re-connected. Project Update #2 (PDF)
  • UPDATE (March 25, 2019): Permanent easement cleared. Some large tree removal. Depending on weather, contractor will start digging and installing sewer main this week (3-25-19). Project Update (PDF)

PROJECT DESCRIPTION: Installation of 8″ sewer main and connection of private sewer services.

BEGINNING DATE: McInroy Construction scheduled to start March 16th –  120 Days to complete (July 16).

PROJECT LOCATION: Three areas: 700-1100 S Clay, S Lynn & E. Sycamore to S Elm. S Alma from E. Austin to E. Berry St

Clay Sewer Project Updates

 

PROJECT: Water Plant Piping Upgrade.