PROJECT: Clay Street Sewer Phase II.

  • UPDATE (April, 15 2019): 880′ of line installed. Four (4) manholes placed. Services re-connected. Project Update #2 (PDF)
  • UPDATE (March 25, 2019): Permanent easement cleared. Some large tree removal. Depending on weather, contractor will start digging and installing sewer main this week (3-25-19). Project Update (PDF)

PROJECT DESCRIPTION: Installation of 8″ sewer main and connection of private sewer services.

BEGINNING DATE: McInroy Construction scheduled to start March 16th –  120 Days to complete (July 16).

PROJECT LOCATION: Three areas: 700-1100 S Clay, S Lynn & E. Sycamore to S Elm. S Alma from E. Austin to E. Berry St